Despite downturns in other markets, IT services continue to grow, and the demand for more data center space and power grows right along with it.
Breaking ground in January of this year, the primary room construction is complete with the addition of the raised floor.
60 tons of HVAC, UPS and more backup power generation (1MW) are in the works, and expected to be fully operational by the beginning of Q3.